You have processed checks. You have the checks in hand. However the process was interrupted and now the status of the check batch says printing.
Click on the MS Dynamics GP button. Go to Tools – Routines – Batch Recovery. If the batch is listed there mark the batch and click process or continue.
I have found it helpful at this point to do two things. One, do a complete backup of the company database, especially if you have a large check batch. Two, check links the Purchasing Transaction Logical file in Maintenance – Check Links – Purchasing series.
At this point you should be able the Post the checks. Go to Transactions – Purchasing – Post Checks. Select the batch, then click Process. If you have not printed the remittance advice report you will be prompted to print it. This is required. Make sure to change the selection to Remittance Form and off Remittance Alignment Form. Once you have printed the remittance click Post, and then Process.
Here it the MS Techknowledge article ID 855595 which could be helpful.
SYMPTOMS
You continue to receive this message even after you try the busy batch procedures.
For more information about the busy batch procedures, click the following article number to view the article in the Microsoft Knowledge Base:
MORE INFORMATION
You can select the batch in the Post Payables Checks window. To do this, click Transactions, click Purchasing, and then click Post Checks.
You cannot select the batch in the Batches window. If you try to do this, you receive the following warning message: